We will design the S74 in Kielce

We will design the Kielce Zachód - Kielce section of the S74 expressway. At the end of January, we signed a contract with PUT Intercor, the contractor for the project, which is being implemented in the 'design and build' format.

We will design the Kielce Zachód – Kielce section of the S74 expressway. At the end of January, we signed a contract with PUT Intercor, the contractor for the project, which is being implemented in the ‘design and build’ format. We are responsible for the comprehensive preparation of the multi-industry design documentation for this construction project and for exercising author supervision. The scope of project work includes:

The section of the S74 expressway will be 5 km long and will connect the Kielce Zachód and Bocianek junctions. Most of the route will be constructed in excavations to reduce the inconvenience of the route for local residents. Two tunnels and two road junctions are also planned. Most of the existing junctions with the planned route will be kept at the same level. 

The investment, worth around PLN 713 million, should be completed within 36 months. We have 10 months to prepare the documentation and apply for the Road Project Permit. 

Autor: lafrentz
Data: 25.04.2024